top of page

1.       New Sites (Including new towers and new shelters) Review the design drawing of new towers.The standard design for the foundation w as checked according to the soil report submitted by the Subcontractor.  Pay a visit, as the case may be, to the Site to check the foundation works. Pay a visit, as the case may be, to the Site after removing the form work to check the concrete surface before back filling which must be new clean sand. Pay a visit, as the case may be, to the Subcontractor’s workshop during fabrication to inspect the fabrication of the steel members and test the welded elements by penetration spray chemicals and check the certificates and tests done by the Subcontractor for materials and bolts. Pay a visit, as the case may be, to the Site to examine the erection procedures and check the material list for the delivered members. Pay a visit, as the case may be, to the Site after completion for handing over, collecting, checking and approving the as built drawings.

2. Existing Sites (Including existing towers and new shelters) Pay a visit or visits, as the case may be, to the Site to verify the measurements taken by the Subcontractor.Review the calculation note for checking the design submitted by the Subcontractor; Pay a visit or visits, as the case may be, to the site to check the strengthening for existing towers if   any. Pay a visit or visits, as the case may be, to the Site to examine the erection procedures for shelter sand check the material list for the delivered members. Pay a visit or visits, as the case may be, to the Site after completion for handing over, collecting, checking and approving the as built drawings.

3.Rooftop Sites (Including new masts and new shelters) Pay a visit or visits, as the case may be, to the Site to verify the measurements taken by the Subcontractor.Review the design submitted by the Subcontractor.Pay a visit or visits, as the case may be, to the Site to examine the erection procedures and check the material list for the delivered members.Pay a visit or visits, as the case may be, to the Site after completion for handing.

Codes and Standards:

TIA-EIA -222F

Software:

SAP2000

AutoCAD 

TST

Client:

EGYPT  TELECOM

Main Contractor:

HUAWEI TECHNOLOGY

bottom of page